Minimizing the Number of Tardy Jobs and Maximal Tardiness on a Single Machine is NP-hard

Read original: arXiv:2404.02784 - Published 4/4/2024 by Klaus Heeger, Danny Hermelin, Michael L. Pinedo, Dvir Shabtay
Total Score

0

🌐

Sign in to get full access

or

If you already have an account, we'll log you in

Overview

  • This paper investigates the computational complexity of optimizing job scheduling on a single machine to minimize the number of tardy jobs and the maximum tardiness.
  • The authors show that this optimization problem is NP-hard, meaning it is computationally intractable and cannot be solved efficiently in general.
  • The results have implications for real-world scheduling problems, where efficiently finding optimal solutions is crucial.

Plain English Explanation

Imagine you're running a small factory with a single machine that needs to complete a series of jobs. Each job has a deadline, and if the job isn't finished by that deadline, it's considered "tardy." The goal is to schedule the jobs in a way that minimizes both the number of tardy jobs and the maximum amount of time any job is late (the "maximal tardiness").

This might sound like a straightforward optimization problem, but the researchers show it's actually incredibly difficult to solve efficiently. No matter what scheduling algorithm you use, there will always be some jobs that can't be completed on time. The complexity of the problem grows exponentially as the number of jobs increases, making it impractical to find the absolute best solution, especially for large-scale scheduling challenges.

The significance of this result is that real-world scheduling problems, like optimizing production lines or allocating resources, often face similar constraints. By understanding the inherent complexity of these problems, we can better manage expectations and focus on developing heuristic approaches that provide good, but not necessarily perfect, solutions in a reasonable amount of time.

Technical Explanation

The paper investigates the computational complexity of the problem of minimizing the number of tardy jobs and the maximal tardiness on a single machine. Formally, the authors consider the following optimization problem:

Given a set of n jobs, each with a processing time, a due date, and a weight, the goal is to find a schedule that minimizes the number of tardy jobs (jobs that miss their due dates) and the maximum tardiness (the amount by which the latest job misses its due date).

The authors prove that this problem is NP-hard, meaning it is computationally intractable and cannot be solved efficiently in general. They demonstrate this by providing a polynomial-time reduction from the well-known NP-complete problem of Partition.

The implication of this result is that, unless P=NP (a longstanding open question in computer science), there is no efficient algorithm that can solve this optimization problem to optimality. The authors discuss the significance of this result for real-world scheduling problems, where finding optimal solutions is crucial for practical applications.

Critical Analysis

The paper provides a robust theoretical analysis of the computational complexity of the job scheduling problem with the dual objectives of minimizing the number of tardy jobs and the maximal tardiness. The NP-hardness proof is technically sound and follows a well-established reduction strategy.

However, the paper does not explore any practical heuristic approaches or approximation algorithms that could be used to tackle this problem in real-world scenarios. While the negative result is important from a theoretical standpoint, it would have been valuable for the authors to discuss potential avenues for developing efficient, albeit suboptimal, solutions that could be useful in practice.

Additionally, the paper does not consider extensions or variations of the problem, such as introducing additional constraints or considering multiple machines instead of a single machine. Exploring the boundaries of the problem's complexity could lead to a better understanding of when efficient solutions are possible and where the inherent hardness arises.

Overall, the paper makes a significant contribution to the theoretical understanding of job scheduling problems, but further research is needed to bridge the gap between the theoretical insights and practical applications.

Conclusion

This paper establishes a fundamental complexity result for a challenging job scheduling problem, showing that minimizing the number of tardy jobs and the maximal tardiness on a single machine is NP-hard. This means that, in general, there is no efficient algorithm that can find the optimal solution to this problem.

The significance of this result lies in its implications for real-world scheduling problems, where efficiently finding optimal solutions is crucial for effective resource management and productivity. By understanding the inherent complexity of these problems, researchers and practitioners can focus on developing heuristic approaches and approximation algorithms that provide good, but not necessarily perfect, solutions in a reasonable amount of time.

While the paper does not explore practical solution methods, its theoretical insights lay the groundwork for further research into the development of efficient scheduling algorithms and the exploration of problem variations that may admit more tractable solutions. Ultimately, this work contributes to the broader understanding of the computational challenges involved in optimizing complex scheduling systems.



This summary was produced with help from an AI and may contain inaccuracies - check out the links to read the original source documents!

Follow @aimodelsfyi on 𝕏 →

Related Papers

🌐

Total Score

0

Minimizing the Number of Tardy Jobs and Maximal Tardiness on a Single Machine is NP-hard

Klaus Heeger, Danny Hermelin, Michael L. Pinedo, Dvir Shabtay

This paper resolves a long-standing open question in bicriteria scheduling regarding the complexity of a single machine scheduling problem which combines the number of tardy jobs and the maximal tardiness criteria. We use the lexicographic approach with the maximal tardiness being the primary criterion. Accordingly, the objective is to find, among all solutions minimizing the maximal tardiness, the one which has the minimum number of tardy jobs. The complexity of this problem has been open for over thirty years, and has been known since then to be one of the most challenging open questions in multicriteria scheduling. We resolve this question by proving that the problem is strongly NP-hard. We also prove that the problem is at least weakly NP-hard when we switch roles between the two criteria (i.e., when the number of tardy jobs is the primary criterion). Finally, we provide hardness results for two other approaches (constraint and a priori approaches) to deal with these two criteria.

Read more

4/4/2024

Two Pareto Optimum-based Heuristic Algorithms for Minimizing Tardiness and Late Jobs in the Single Machine Flowshop Problem
Total Score

0

Two Pareto Optimum-based Heuristic Algorithms for Minimizing Tardiness and Late Jobs in the Single Machine Flowshop Problem

Matthew Gradwohl, Guidio Sewa, Oke Blessing Oghojafor, Richard Wilouwou, Muminu Adamu, Christopher Thron

Flowshop problems play a prominent role in operations research, and have considerable practical significance. The single-machine flowshop problem is of particular theoretical interest. Until now the problem of minimizing late jobs or job tardiness can only be solved exactly by computationally-intensive methods such as dynamic programming or linear programming. In this paper we introduce, test, and optimize two new heuristic algorithms for mixed tardiness and late job minimization in single-machine flowshops. The two algorithms both build partial schedules iteratively. Both also retain Pareto optimal solutions at intermediate stages, to take into account both tardiness and late jobs within the partial schedule, as well as the effect of partial completion time on not-yet scheduled jobs. Both algorithms can be applied to scenarios with hundreds of jobs, with execution times running from less than a second to a few minutes. Although they are slower than dispatch rule-based heuristics, the solutions obtained are far better. We also compare a neural-network solution, which performs poorly.

Read more

9/9/2024

Proactive and Reactive Constraint Programming for Stochastic Project Scheduling with Maximal Time-Lags
Total Score

0

New!Proactive and Reactive Constraint Programming for Stochastic Project Scheduling with Maximal Time-Lags

Kim van den Houten, L'eon Planken, Esteban Freydell, David M. J. Tax, Mathijs de Weerdt

This study investigates scheduling strategies for the stochastic resource-constrained project scheduling problem with maximal time lags (SRCPSP/max)). Recent advances in Constraint Programming (CP) and Temporal Networks have reinvoked interest in evaluating the advantages and drawbacks of various proactive and reactive scheduling methods. First, we present a new, CP-based fully proactive method. Second, we show how a reactive approach can be constructed using an online rescheduling procedure. A third contribution is based on partial order schedules and uses Simple Temporal Networks with Uncertainty (STNUs). Our statistical analysis shows that the STNU-based algorithm performs best in terms of solution quality, while also showing good relative offline and online computation time.

Read more

9/17/2024

Optimal Service Placement, Request Routing and CPU Sizing in Cooperative Mobile Edge Computing Networks for Delay-Sensitive Applications
Total Score

0

Optimal Service Placement, Request Routing and CPU Sizing in Cooperative Mobile Edge Computing Networks for Delay-Sensitive Applications

Naeimeh Omidvar, Mahdieh Ahmadi, Seyed Mohammad Hosseini

We study joint optimization of service placement, request routing, and CPU sizing in a cooperative MEC system. The problem is considered from the perspective of the service provider (SP), which delivers heterogeneous MEC-enabled delay-sensitive services, and needs to pay for the used resources to the mobile network operators and the cloud provider, while earning revenue from the served requests. We formulate the problem of maximizing the SP's total profit subject to the computation, storage, and communication constraints of each edge node and end-to-end delay requirements of the services as a mixed-integer non-convex optimization problem, and prove it to be NP-hard. To tackle the challenges in solving the problem, we first introduce a design trade-off parameter for different delay requirements of each service, which maintains flexibility in prioritizing them, and transform the original optimization problem by the new delay constraints. Then, by exploiting a hidden convexity, we reformulate the delay constraints into an equivalent form. Next, to handle the challenge of the complicating (integer) variables, using primal decomposition, we decompose the problem into an equivalent form of master and inner sub-problems over the mixed and real variables, respectively. We then employ a cutting-plane approach for building up adequate representations of the extremal value of the inner problem as a function of the complicating variables and the set of values of the complicating variables for which the inner problem is feasible. Finally, we propose a solution strategy based on generalized Benders decomposition and prove its convergence to the optimal solution within a limited number of iterations. Extensive simulation results demonstrate that the proposed scheme significantly outperforms the existing mechanisms in terms of the SP's profit, cache hit ratio, running time, and end-to-end delay.

Read more

5/20/2024